Island Road Building - Brooks Bay

SIZE: $4.5 million
DURATION: mid 2023 through 2024
CLIENT: Mosaic Forest Management

Way Key Sand & Gravel utilizes a crew of 9 with 11 pieces of equipment in Brooks bay to build mainline forest road. This includes drilling and blasting, as well as spreading, compacting, grading, ditching, and culvert / bridge install. The team accesses the work site each morning using one of our crew boats. 

PREVIOUS Forestry Services
NEXT Quinsam Industrial Park Remediation